A major gas producer needed to expand an existing railcar
loading yard with a 600' long, 20+ position railcar load
rack including connecting pipe and a 180' walkway. Project
criteria included: x-ray quality welding, fast delivery,
minimum disruption of loading operations, safety and
environmental compliance and competitive cost. We designed
the foundations, loading rack and walkway with
pre-installed pipe. We fabricated the pipe, walkways, supports,
ladders, stairs, safety bridge gangways and handrails in our shop. Our installation
crew required only 4 men working three weeks to finish the
project.
All project goals were met.